Posted - 2005-10-31 : 18:54:09
Chris S writes "I have a sales database on one SQL Server that is going to query off from numerous tables on an accounting database that resides on another SQL Server. When a end user modifies a table on the accounting database I want the sales database to get the update in their queries. If this creates too much overhead I would like the accounting database to update the sales database every 30 minutes. I heard this can be done without using replication so what do you suggest? Triggers?"

spirit1
Cybernetic Yak Master

11752 Posts

Posted - 2005-10-31 : 19:39:42
depends on how soon do you need changes to synchronize.
i'd go with replication.

Go with the flow & have fun! Else fight the flow
Go to Top of Page

derrickleggett
Pointy Haired Yak DBA

4184 Posts

Posted - 2005-10-31 : 20:30:57
The accounting database should have history detail if it's a decent accounting system. You could just run a job that captures data between x and y times ever 30 minutes. There are a lot of possibilities to this answer. How many records are you talking about? What does the design of the two systems look like? Are there any conversions between the two systems? etc, etc, etc