 SQL Server Agent Job to schedule to end at a partr

Author  Topic 

nvasuki
Starting Member

1 Post

Posted - 2008-08-13 : 07:28:09
I have a reindex job in SQL Server 2005 and I need it to stop by 6.30 A.M because I have my schedule backup by 7 A.M. So whether the reindex completes or not I want to stop it by 6.30 A.M.
Please help me on How to do it

spirit1
Cybernetic Yak Master

11752 Posts

Posted - 2008-08-13 : 08:13:56
in scheduling options under daily frequency set it to stop at 6:30

_______________________________________________
Causing trouble since 1980
Blog: http://weblogs.sqlteam.com/mladenp
Speed up SSMS development: www.ssmstoolspack.com <- version 1.0 out!
Go to Top of Page

acollins74
Yak Posting Veteran

82 Posts

Posted - 2008-08-13 : 08:18:34
thinking out loud.
wouldn't this stop force a kill on the associated spid introducing rollback.
Go to Top of Page

sodeep
Master Smack Fu Yak Hacker

7174 Posts

Posted - 2008-08-13 : 14:38:04
Thats right.
Go to Top of Page

rmiao
Master Smack Fu Yak Hacker

7266 Posts

Posted - 2008-08-13 : 22:50:04
You can change start time, job history will tell you took how long to run it.