Posted - 2001-10-12 : 02:40:28
I have a project budget and <=6 milestones which consist of a description, date of completion and the total % of the budget that will be used up at completion of that milestone.
eg Budget = $10 000
Descript | Date | Percent
------------------------------
Mile1 1 Jan 5
Mile2 2 Feb 24
Mile3 26 Feb 48
Mile4 1 Apr 67
Mile5 23 Apr 85
Mile6 5 May 100

From this I need to generate a planned monthly expenditure, per project or for all projects grouped together.

Anyone with any ideas.
Thanks

   