Please start any new threads on our new
site at https://forums.sqlteam.com. We've got lots of great SQL Server
experts to answer whatever question you can come up with.
Author |
Topic |
imughal
Posting Yak Master
192 Posts |
Posted - 2013-06-03 : 06:55:35
|
Hi,I have setup SQL Server 2012 AG with 2 node. Mirroring is set as Synchronous Commit. I have used 1 TB disc on both server. Now i am going to add 3rd node as DR node.For 3rd DR Node i have 500 GB Space. Please will it be ok to install and add 3rd node with less space. OR Space should be same as other node.Right now i m using 200 GB and growth is not such.Secondly when i add 3rd DR node how and where i specify mirroring as Asynchronous.Please guide.Thanks |
|
|
|
|