Posted - 2009-05-01 : 07:00:51
|
Hi, I wonder if anybody would be kind enough to help me please.Up until yesterday my hosting company was using sql 2000 and I used entreprise manager every few days to update some of the data held within 400 rows in a table. This worked great, I could simply cut and past rows if I wanted to replicate certain rows before making changes or just change the data in a field.Now all this seems to be lost with management studio express 2008...I need to edit about 400 rows. Is there an easy way around this?many thanks |
|
simy
Starting Member
2 Posts |
Posted - 2009-05-01 : 07:06:59
|
I think I've just found the solution. Go to tools - options - SQL server Oject Explorer and change 200 to 400. |
|
|
|
|
|